2022 Budget in Brief
FERNWAY ROAD WORK TIMELINE FERNWAY ROAD WORK TIMELINE
In 2021, phase six of nine in the Fernway Road Work was accomplished in the Fernway
Construction is expected to begin, at the earliest, in late April to early May. The entire project is expected to be substantially complete by the end of August 2022. A final landscape restoration, which involves placing topsoil and sodding new ditches, is planned to take place during late September through early October of 2022. Compared to years prior, this projects has a substantially longer duration due to the increased size of the project. Previously, these projects were much smaller. The Village is reconstructing the last three regions of Fernway in one year, whereas in the past the approach has been to complete one region per year.
This project has been in the works since 2019, providing a full reconstruction to roads within the Fernway subdivision in Orland Park. The subdivision, originally constructed in the 1960s will be receiving repairs to roads while also addressing ditch and drainage concerns. Previous repairs from 2019 included a full pavement reconstruction with the addition of concrete shoulders to support the pavement edge and the construction of a new parking lot adjacent to Wlodarski Park at the northeast corner of 167th Street and Robinhood Drive. For more information regarding this development, please contact Public Works at 708-403-6350.
Subdivision, overseen by the Public Works Department. This included stormwater improvements and road repairs. In addition, the design of work for phases seven through nine was completed to prepare for construction in 2022. The project first began in 2016, completing phases one through five. The 2022 portion of this project is currently in design with V3 Companies. V3’s survey crew is presently gathering field information in Orland Park during late 2021 into early 2022. The design is expected to be completed by March 2022 in preparation to solicit bids for the construction in Spring of 2022.
MARCH 2022
APRIL - MAY 2022
DEC 2021 - FEB 2022
FIELD INFORMATION GATHERING
DESIGN COMPLETED FOR BIDS
CONSTRUCTION BEGINS
Field information is currently being gathered by V3 Companies and is expected to be complete in early 2022.
The design is expected to be completed by March 2022 in preparation to solicit bids for the construction in Spring of 2022.
Construction can be expected to begin, at the earliest, in late April to early May.
34
VILLAGE OF ORLAND PARK | FISCAL YEAR 2022 BUDGET IN BRIEF
Made with FlippingBook Digital Publishing Software